Project Overview
This project involved the stringing of a 132 kV overhead transmission line (OHL) between Qurum and Muttrah, two key regions in Muscat, Sultanate of Oman. The project was critical in strengthening the local power transmission network and ensuring reliable supply to densely populated and commercial zones.
Scope of Work
-
Precision conductor stringing across challenging urban terrain.
-
Utilization of advanced tensioner-puller equipment to maintain line safety and performance.
-
Strict compliance with OETC technical and safety standards.
-
Coordination with the main contractor, Galfar, to ensure smooth integration with other civil and electrical works.
Challenges & Solutions
-
Urban Environment: Working within city limits required careful planning to avoid disruptions. Our team implemented night works and special safety measures.
-
Space Constraints: Limited work areas were managed using specialized compact equipment and skilled manpower.
-
Continuity of Supply: Stringing activities were planned to avoid any interruptions to the existing power network.
Outcome
The project was delivered on time and with high precision, reinforcing Powerway’s reputation for excellence in 132 kV transmission line projects. It significantly improved grid reliability and supported Muscat’s growing residential, commercial, and industrial power demand.