Client: OETC
Main Contractor: SNCC
Project Overview
This project involved the erection and stringing of a 400 kV Overhead Transmission Line connecting Sohar Free Zone to Mahadah Grid Station. The scope required constructing a critical high-voltage link to strengthen Oman’s power transmission network and support industrial growth in Sohar Free Zone.
Scope of Work
-
Tower Erection: Complete assembly and installation of 400 kV transmission towers.
-
Conductor Stringing: Precise stringing of high-voltage conductors across long spans with safety and accuracy.
-
Insulation & Hardware Fittings: Installation of insulators and associated hardware to meet OETC standards.
-
Testing & Commissioning Support: Ensured quality compliance and smooth integration with the national grid.
Key Challenges & Achievements
-
Managed heavy tower erection and conductor stringing over difficult terrain and long spans.
-
Maintained strict compliance with OETC safety guidelines and international standards.
-
Completed works within stipulated timeline ensuring uninterrupted project progress for the main contractor SNCC.
-
Enhanced the grid reliability and capacity to meet the rising demand in Sohar’s industrial and commercial zones.
Outcome
The successful completion of this 400 kV line significantly improved the transmission capacity and power reliability in Northern Oman. It played a vital role in supporting the energy needs of Sohar Free Zone and surrounding areas, reinforcing Powerway Enterprises LLC’s reputation as a trusted partner in high-voltage infrastructure projects.