Powerway Enterprises LLC

OPGW Conductor Replacement (Bu Ali – Al Kamil)

Client: OETC
Main Contractor: Majan Telecommunication


Project Overview

This project involved the replacement of Optical Ground Wire (OPGW) conductors along the Bu Ali – Al Kamil transmission line in Oman. OPGW is a critical component that combines the functions of a traditional ground wire with a high-capacity optical fiber for reliable communication and protection in the power grid.


Scope of Work

  • Careful removal of existing OPGW conductor without disrupting ongoing power transmission.

  • Installation of new OPGW cables along the transmission line route.

  • Splicing, termination, and testing of fiber optic links to ensure uninterrupted data communication.

  • Coordination with live-line operations to maintain safety and system stability.


Challenges & Solutions

  • Live Line Safety: Our experienced team worked under strict OETC safety guidelines to prevent risk during replacement on energized lines.

  • Fiber Integrity: Advanced splicing and OTDR testing ensured optimal performance of optical fibers with minimal signal loss.

  • Time Sensitivity: Replacement works were completed within tight deadlines to minimize disruption to transmission operations.


Outcome

  • Successful installation of high-quality OPGW conductors along the Bu Ali – Al Kamil line.

  • Enhanced communication and protection for OETC’s transmission network.

  • Project delivered on time, safely, and to international standards, reinforcing Powerway’s expertise in OPGW solutions.